Skip to content

Price bands (lower price after a number of copies)

Charge the first copies at one price and the copies above a number at another, e.g. the first 10,000 mono at 0.6p and the rest at 0.5p. On the customer's price list or on one machine's own price.

Where: Customer › Contracts & invoices › Copy prices › Price bands, or Contract › Machines & pricesFor Owners, admins

Step by step

  1. Set the meter's price per copy first (on the customer's Copy prices, or This machine only on the contract).
  2. Under Price bands (customer) or under the machine's meter (contract), press + Add price band.
  3. Enter From copies (e.g. 10000) and the Price per copy from there on (e.g. 0.005), then press Add band.
  4. Add more bands the same way (up to 10). Press Remove on a band to take it off.

How a period is priced

Free copies come off first. The copies left are priced band by band: up to the first band at the meter's price, then each band's price from its number on.

Example: 25,000 copies, 1,000 free, bands from 10,000 at 0.005 and from 20,000 at 0.004, price 0.006: 10,000 × 0.006 + 10,000 × 0.005 + 4,000 × 0.004 = £126.00.

Bands count per machine per billing period. When the contract pools copies, they count on the pooled total.

The billing run and the invoice line show the breakdown, e.g. "10,000 at 0.006 + 10,000 at 0.005 + 4,000 at 0.004".

Changes

Bands apply from the next billing run; finalised runs keep what they used. A yearly price increase raises the bands too.

A machine set back to the customer's price list uses the customer's bands.